DragonFly - Big-Picture Status

This section lists project (self) assignments and sub-projects that we have brainstormed about that developers could dig their teeth in to. Related discussions will be in the kernel list and submissions should be posted to the submit list.

Label Work Unit Developer Requirements StartDate EndDate Status
RCNG Merge 5.x RCNG Robert Garrett None 17-Jul-2003 xx-Jul-2003 Completed
DEV1 Core Messaging / DEV Wrapper Matthew Dillon None 17-Jul-2003 None In Progress
SYSCALL1 Syscall Messaging & Wrapper Matthew Dillon DEV1 17-Jul-2003 None In Progress
VFS1 VFS Messaging & Wrapper Matthew Dillon SYSCALL1 17-Jul-2003 None Not started
NOSECURE NOSECURE build variable removal Jeroen Ruigrok van der Werven None 2-Aug-2003 3-Aug-2003 Completed
KERBEROSIV Kerberos IV removal Jeroen Ruigrok van der Werven NOSECURE 5-Aug-2003 10-Aug-2003 Completed
SLAB Slab Allocator for Kernel Matt Dillon   25-Aug-2003 31-Aug-2003 Completed
NETNS Fix NETNS David Rhodus   6-Sept-2003 7-Sept-2003 Completed